Great Australia Mine – CIL Upgrade Project

Como Engineers > Projects > Great Australia Mine – CIL Upgrade Project
2017
Cloncurry (North Queensland), Australia
Client:

CopperChem Pty Ltd

Go back to projects Printable Version

The Great Australia Mine Gravity Circuit Project integrated a new gravity circuit into the existing grinding and classification circuit.

The works involved with this project included: The Great Australia Mine CIL Upgrade Project upgraded the existing copper flotation plant to a gold CIL plant.

The works involved with this project included:

  • Refurbishment of existing crushing, grinding and classification circuits.
  • Construction of 8 off leach/CIL tanks.
  • Supply & install tank agitators.
  • Supply & install mechanically wiped interstage screens.
  • Supply and install vibrating trash, loaded carbon and carbon safety screens.
  • Cyanide mixing, storage and dosing system.
  • Cyclone tower extension for future gravity upgrade.
  • Design, fabricate, construct and commission a new modular 2T Pressure Zadra Stripping circuit with Carbon Regeneration Kiln Design, fabricate, construct and commission a new gravity circuit.

Recent News & Projects

Binduli North Gold Project Pressure Zadra Elution Plant

Binduli North Gold Project - Western Australia

Singida Gold Project Pressure Zadra Elution Plant

Lupa Goldfields of the Songwe District of Central Tanzania