Project
Nordic Mines Gold Project
Location
Laiva in Finland
Client
Metso Minerals Sweden, for Nordic Mines
Contract Value
$3.79m
Commencement Date
October 2010
Practical Completion
April 2011
Job No.
2805

Description
Como Engineers were engaged to provide a Supply of a 6 tonne PLC automated Pressure Zadra System with 300kg/hr LPG fired carbon regeneration kiln and integral goldroom.
All engineering, design, fabrication and construction of the modular gold strip plant
were completed in Perth, WA. The system was then pre-
Project Manager
Sean Galvin