Project
Jaguar Copper / Zinc Plant
Location
North Eastern Goldfields, WA
Client
Jabiru Metals
Contract Value
$9.3m
Commencement Date
December 2010
Practical Completion
Ongoing
Job No.
2753



Description
Como Engineers were awarded the contract to complete the detailed engineering design, supply and construction of the HMS plant at Jabiru Metals, Jaguar Mine north of Kalgoorlie.
The plant has two main sections; three stage crushing, conveyors, screens and bins, feeding a modular 50tph HMS with a total project value of approximately $9.5M.
Como Engineers also successfully completed the Scoping Study and DFS for the HMS Plant earlier this year with commissioning scheduled for December quarter 2011.
A perfect example of how Como Engineers prides itself on being a company that can deliver from “Concept to Completion”.
Project Manager
Grant Blakeman